The TMMOB Trabzon Provincial Coordination Board released its technical warnings regarding the $1 billion New Trabzon Airport project. The Chamber of City Planners filed a lawsuit seeking the annulment of the EIA decision, citing the 300-hectare sea land reclamation and the lack of examination of alternative sites.
Trabzon Seyret··translated from Turkish
- The TMMOB Trabzon Provincial Coordination Board presented its joint evaluation report on the New Trabzon Airport project.
- The Chamber of City Planners Headquarters announced that a lawsuit was filed seeking the cancellation of the project's 'EIA Positive' decision.
- Chambers called for upgrading the existing runway and transparent planning instead of the 300-hectare sea reclamation.

The TMMOB Trabzon Provincial Coordination Board held a joint evaluation meeting regarding the New Trabzon Airport project planned for construction in the city. The technical dimensions of the project were scrutinized during the meeting, which was attended by representatives of the Chamber of Architects, the Chamber of City Planners, the Chamber of Civil Engineers, the Chamber of Geological Engineers, and the Chamber of Geophysical Engineers.
The investment, which previously had its Environmental Impact Assessment process approved, is planned to be implemented with an estimated budget of around $1 billion and aims to establish a new 3,240-meter-long runway. However, the professional chambers drew attention to the fact that approximately 300 hectares of the total 410-hectare project area will be built on sea land reclamation.
Chamber of City Planners files lawsuit
Speaking at the meeting, Ersin Türk, Head of the Trabzon Branch of the Chamber of City Planners, announced that legal action had been taken at the headquarters level seeking the annulment of the “EIA Positive” decision. Stating that they are not categorically opposed to the project, Türk noted that they identified technical deficiencies in the prepared report:
“We know that Trabzon needs a new runway and airport. However, alternative routes were not sufficiently examined in the prepared EIA dossier. Roughly 300 hectares of sea reclamation will cause both severe coastal destruction and high costs. We do not find it right that this decision was made without transparently discussing the areas south of the existing runway or other options.” Ersin Türk
Serbülent Vural, Head of the Trabzon Branch of the Chamber of Architects, stated that local dynamics and professional chambers should not be excluded from mega-projects that shape the city’s future. Vural demanded that the project clearly demonstrate how the new airport will integrate with the Trabzon Light Rail System and the planned Southern Ring Road corridor.